Monday, November 28, 2016

Display Maintenance Plans


1. Tcode: IP03

  • Enter plant maintenance number you wish to display
  • Press enter or click check button at the top


2. Navigate the tabs you wish to view the details


----------- done ------------

Change Maintenance Plan


1. Tcode: IP02

  • Enter the Maintenance Plan number you wish to edit or update



2. Select the tabs you wish to update

  • Update the call horizon
  • Enter how many months this schedule will run in Scheduling period


3. Save

Schedule Maintenance Plan


1. Tcode: IP10

  • Enter the Maintenance Plan number
  • Press enter or the check button at the top



2. Click the Start button




3. Enter or edit the desired Start Cycle date



4. The schedule list will be populated with the plan date

  • System will show the plan for the planned duration of 15 months, plan for carrying out maintenance every month.



5. Select the first row with the scheduling type of "New start Hold"

  • Click the release button


6. Scheduling Type will change to New start Save to call

  • Save the schedule


-----------------done--------------

Sunday, November 27, 2016

Display Maintenance Order


1. Tcode: IW33

  • Enter the order number you wish to display


2. Navigate the tabs to view the details of the order



-------------------- done ------------------

Change Maintenance Order


1. Tcode:  IW32

  • Enter the order number you wish to edit and press enter key


2. Navigate the tabs where you wish to edit or update the field

  • In this example, click the Operation tab and add operation



------------ done --------------

Create Single Cycle Plan

1. Tcode: IP41

  • Leave the Maintenance plan empty, this will automatically generated by the system
  • Select the Maintenance Plan Category to : PM Maintenance Order


2. Below screen will be shown, fill up the required data

  • Enter the Maintenance Plan description
  • Enter the Cycle and the Unit of the cycle
  • Enter the Cycle text
  • Enter the Maintenance Item description
  • Enter the Equipment number (After you have entered the equipment number the Planning data will automatically filled up base from the master data record from the equipment master


3. Select Task List

  • Select the Task List for this maintenance plan by clicking GrpCr button


4. Click execute button



5. Double-click the task list description you wish to attach to the maintenance plan



6. You will find at the bottom the task list was attached to this maintenance plan


  • Save the maintenance plan


  • Enter the date when the Cycle will start
  • Click check button to continue saving



------------------- done ----------------

Display General Task List


1. Tcode: IA07

  • Enter the Task List group
  • Press enter or click check button at the top


2. Select the Task List you wish to display

  • After selecting the Task List click the Operation button


3. This will display the lists of operations within the task list


----------- done ------------