Saturday, November 26, 2016

Create General Task List in existing Task List group


1. Tcode: IA05


  • Enter the Task List group where you want to put the new task list you wish to create
  • Press enter or the check button at the top



2. Click the New Entries button



3. Fill up the required data for this new task list

  • Enter the group counter description
  • Enter the Plant
  • Enter the Work Center and Plant
  • Enter Usage: 4 - Plant maintenance
  • Enter Status: 4 - Release (general)
  • Click Operation button



4.  Fill up the operations needed to the task



  • Enter the operation description
  • Enter number work
  • Enter the unit of work
  • Enter how many person will work
  • Enter the Calculation to 1, it will automatically calculate the duration of work

 5. Save


------------- done ---------------